The General Contractor |
|
|
General Contractors coordinate
and supervise the work at
construction sites from early
development to final product.
Before contractors begin a
project, they must submit a bid
to the University Facilities,
Project Services. The lowest
bid is usually, but not always,
accepted. Other factors, such
as the quality of a contractor's
past work, may be taken into
account.
General contractors are
responsible for securing all job
site materials, obtaining all
necessary permits and licenses
for construction and seeing that
building codes and safety
regulations are followed.
The General Contractor also
hires all required
subcontractors and must
coordinate the construction schedule, making sure the
subcontractors are at the
building site when needed so
that the project remains on
schedule. The sequencing of
construction and the supervision
of the work that the
subcontractors perform are key
roles for the general
contractor.
General Contractors who are
interested in working for
Rutgers University must follow
the procedures identified below:
|
 |
The Pre-Qualification Process
1.
General Contractor must submit a
Letter of Interest to
University Facilities,
attention: Karen Bartok:
kbartok@facilities.rutgers.edu
2.
A Pre-Qualification Package
is sent all General Contractors
who have submitted their
Letter of Interest.
3.
The Pre-Qualification Package
is completed and sent back to
University Facilities
4.
General Contractor
Pre-Qualification Package is
accepted and a
Pre-Qualification Interview
is granted.
5.
Interview is conducted,
references and licenses checked
and General Contractor is
approved and added to the
General Contractor Database,
sorted by specialty type.
|
 |
The Bidding Process – Selecting
the General Contractor
The Bid Package is assembled by the Contract Administrator
and is sent to all selected
General Contractors.
1.
University Facilities issues a
letter to the General
Contractors noting that Bid
Set Drawing Prints and
Specifications are available
for access on the Online Plan
Room
2.
University Facilities issues
step by step instructions
(including the password) to aid
General Contractors in accessing
Online Plan Room drawings
and specifications
.
3.
General Contractors order Bid
Set Drawing Prints and
Specifications online
directly from the Triangle
Web Site
4.
Triangle will deliver requested
hard copy Bid Set Drawing
Prints and Specifications to
the General Contractors.
Sub-Contractors may elect to
view the drawings on-line rather
than receive hard copies.
5.
The General Contractor submits a
bid to the University Facilities
Contract Administrator.
6.
The Bid is opened during a
meeting chaired by University
Facilities.
|
 |
Bid
Review & General Contractor
Contract Award
After the Bids have been reviewed by the Working Group who
consist of stakeholders and
University Facilities Staff, the
successful General Contractor
will be notified and a
preliminary contract will be
drafted. The Contract Award
must be approved by the
Buildings and Grounds Committee
of the Board of Governors. Once
approved, the final Contract is
drafted and awarded to the
General Contractor who is
provided with final five sets of
Contract Documents
(signed/sealed prints and
specifications).
|
 |
Construction
Change Orders to the General
Contractor
1.
As construction progresses,
changes in scope or design may
be required. To accommodate
these changes, a written order
is issued by the Director of
Project Services to the
Contractor. The written order
will address the changes in the
plans or quantities or both,
within or beyond the scope of
the contract and establishes the
basis of payment and time
adjustments for the work
affected by the changes.
2.
A full set of construction
drawings, which incorporate all
changes made during the
construction process as a result
of the issuance of change orders,
field directives, etc
will be provided to University
Facilities at the end of the
construction process.
|
 |
Construction is nearly complete
1.
Punch Lists
The punch list is a list created
at the end of the project. It
contains a list of items or
tasks that need to be repaired
or completed by the General
Contractor. The list is created
by the owner and confirmed by
the General Contractor.
2.
Building Commissioning
Building commissioning verifies
and documents that the new
facility and all of its systems
and assemblies are planned,
designed, installed, tested,
operated, and maintained to meet
the project requirements. This
process is conducted by an
outside agency, not the General
Contractor.
The commissioning process is complete once the Facilities
Operations & Services mechanical
staff has received all
operational manuals and
associated training.
|
 |
1.
Project Close Out
All punch list items have been
completed
2.
Turn Over
The building is officially turned over from the General
Contractor to University
Facilities
3.
Eleven Month Walk Thru
Eleven months about the building has been turned over to the
owner (Rutgers University), the
General Contractor must perform
the End-of-Warranty Walk
Thru.
University Facilities prepares a formal report documenting
recorded and responded to
problems during warranty.
|
|
|
|
I
|
|
|
|
|
|
|